Dowe
 Recommend this page

HEINRICH DOWE

 

When Heinrich Dowe wanted to expand an existing stable within a month and a half, innovative construction specialist Brüninghoff accepted the challenge. After performing the architectural and engineering services, the medium-sized hall construction company manufactured the steel components in its own production plant, delivered and assembled them on site. At the same time, Brüninghoff also used the customer’s preferred construction materials and thus fulfilled the builder’s wishes.

Download the PDF project sheet here Download Download
 

Project:

Expansion of a stable

Architecture:
Brüninghoff GmbH & Co. KG

Primary materials:
Steel
Wood

Construction time:
1,5 months

Service:
Construction and roofing